Minutes of the Infrastructure Stakeholders meeting 2011-02-03

 

Hi,

Here are the minutes for the Infrastructure stakeholders meeting
2011-02-03.

Participants:

Ian Smith
Joey Stanford
Loïc Minier
Steve Langasek
James Westby
Stephen Doel
Mounir Bsaibes
Alexander Sack

Status update on current projects.

  - Good progress on test result tracking, focused on toolchain
    benchmark results
  - ImproveLinaroMediaCreate: moved to maintainence.
  - OverallStatusReporting: good progress but some delay due to extra
    requirements coming in late
  - OurOwnOffspring: blocked on hardware, some discussion of how to best
    proceed with that.

ACTION: James to discuss whether XMs or imx.51 are better
ACTION: James to talk to Stephen and Joey about feasibility of
completing "progress bar colour indicating whether tasks are behind" and
"TR priority related to blueprint priority".

Next projects starting RSN:

  * Patch Tracking
  * Continuous Integration

Proposed next projects:

  * Hwpacks v2
  * BuildFailureBugFiling

Alexander is concerned that we need Gerrit for the Android team to
use. He believes that this is high priority and should be delivered soon
for that team to be effective.

The resolution was to add it as a "Next project", and start the
co-ordination with IS immediately. Engineer time will be spent on it
once an engineer is free. This should mean that gerrit is delivered in a
reasonable timeframe, without dedicating an engineer to it to wait on
IS, and without disrupting other projects too much.

Thanks,

James