← Back to team overview

linaro-infrastructure-stakeholders team mailing list archive

Agenga for stakholders meeting 2011-04-07

 

Hi,

Here's the agenda for today.

https://wiki.linaro.org/Platform/Infrastructure/CurrentProjects

  * Update on current projects
    * OverallStatusReporting - This project is moving to the
      maintainence state as the main needs for this cycle are now
      satisfied. Further changes can still be requested by filing bugs
      on the launchpad-work-items-tracker project.
    * OurOwnOffspring - IS have started work on this again, and have
      completed setup of the master. Work on the slaves is scheduled for
      this week.
    * PatchTracking - There is good progress here and a demo instance is
      set up at http://ec2-184-73-78-92.compute-1.amazonaws.com/metrics/
      I'll be contacting stakeholders for this to discuss what else
      needs to be done. This project will remain on our plate as there
      are still things to do, including final deployment.
    * ContinuousIntegration - Some progress has been made here. Work
      will continue to provide the environment for better automated
      testing of WG output.
    * BuildFailureBugFiling - Good progress has been made. There are a
      few changes to be made after discovering some things with tests on
      real live data by Steve. This is also blocked from completion by a
      re-licensing request that is in front of the board.
    * AndroidBuildInfrastructure and AndroidMirrorService - Good
      progress. The basic features are there to allow the Android team
      to do their work, but there are some changes that have to be made.

  * Update on current IS queue (in priority order)
    1. Porter boxes - all but complete
    2. OurOwnOffspring - in progress
    3. Upgrade of wiki.linaro.org (fixes many bugs, improves search)
       - in progress
    4. Private area for LTs to share hwpacks etc.
    5. PatchTracking deployment
    6. Deploy new dashboard.linaro.org
    7. Gerrit for Linaro
    8. Jenkins for Linaro
    ... everything else

  * Update on the team
    * Michael working with validation for three weeks, perhaps until UDS
    * James Tunnicliffe working with us while Michael is working with
      validation
    * Contract signed with new person, joining some time this month or
      early next month.

  * Proposal for next month
    * OverallStatusReporting moves to maintainence
    * BuildFailureBugFailing likely to move to maintainence during the
      month.
    * PatchTracking has a chance of moving to maintainence during the
      month, but that depends on the stakeholder review of the demo.
    * The next queue currently contains two projects
      * HardwarePacksv2 and Gerrit
    * I propose adding one item to the queue: TestDrive, to make it much
      easier for someone to try out the LEBs, and to ease testing of the
      images we produce.
    * In addition, the Android work will be put on hold until the new
      starter joins. As I said above, the main features are there for it
      to be usable, and we can fix particularly urgent bugs in the
      meantime.

  * Discussion of proposal
  * Discussion of changes to IS priorities
  * Discussion of possible future projects
  * AOB

Thanks,

James





Follow ups

References