linaro-infrastructure-stakeholders team mailing list archive
-
linaro-infrastructure-stakeholders team
-
Mailing list archive
-
Message #00086
Re: Infrastructure Stakeholders Meeting 2011-08-11
On Thu, 11 Aug 2011 08:35:46 -0400, James Westby <james.westby@xxxxxxxxxx> wrote:
> Hi,
>
> Actions from last meeting:
>
> * james_w to work with mounir and michaelh to split up the
> ToolchainBuilds spec to be more manageable: still TODO
>
> Report on current projects:
>
> * Patch Tracking - This is up and running and working well. It is all
> but done, and will be complete a couple of days after Guilherme
> returns from vacation.
> * TestDrive - This is available since the last monthly release. At the
> Connect improvements to the GUI were designed, and will be worked on
> this week.
> * HardwarePacksv2 - After a delay due to vacation, this made progress
> at the Connect. It will hopefully be complete this month.
> * CI with LAVA - This made progress at the Connect with kernel builds
> now being submitted to LAVA. The number of kernels built needs to be
> increased, as well as some improvements to what is there.
> * Configure Gerrit - The switch to Gerrit for the Android team
> happened yesterday. There is still more to do in order to use Gerrit
> fully for its intended purpose, and that will happen this month.
>
> * Next projects
> - Private Hardware Pack Builds - we now have a spec for this and
> work will start once TestDrive GUI has been changed, so next week
> or the week after. We estimate 6 weeks for this once it has started.
> - Improvements to status.linaro.org - This is going to be used to
> bring status.linaro.org inline with the new roadmap process, as
> discussed at the Connect. This will start once the HardwarePacksv2
> work is done.
>
> * IS Queue
> - https://portal.admin.canonical.com/q/linaro
> - Meeting bot - almost complete
> - IRC names metrics - not scheduled
> - pad.linaro.org - not scheduled
> - pruning of builds on maprang (ubuntu-build.linaro.org) - waiting
> on code changes from us
> - Canonical conference line: Chinese numbers don't work - awating
> further info
>
> Proposed changes to the queues
>
> * There is no slot free on the next projects queue, so we don't have
> to decide something to add there at this time.
> * I don't think there is anything more urgent that the current
> projects and next projects that would warrant changing them.
> * The IS Queue is small, and nothing in there is very high priority
> that I know of, so I don't think we need to reprioritise there.
>
> Possible upcoming projects
>
> * Discussion of any projects that people want to propose in the near
> future.
Hi,
Here's what we discussed on possible future projects.
* Page showing all Linaro Infrastructure - Jen is working on something
similar to this for the website, we'll see whether that suits Loic's
needs.
* CI testing of linaro-image-tools - run linaro-image-tools tip every
day to catch problems. Just build the image to start with.
* hwpacks v2 changes
- Loic would like to discuss some changes with Mattias to support
using the hwpacks v2 idea elsewhere. While it is just weekly
meetings and code review Mattias can participate in parallel with
other work.
* offspring->dashboard reporting of build failures.
* offspring->LAVA image pushing for validation.
- asac will submit requests for these projects.
* Ubuntu kernel CI - jcrigby will be doing most of the work here, with
Deepti supporting him. It therefore doesn't need to be tracked as
part of the Infrastructure team, though james_w will monitor to
ensure that assumption is correct.
* Maintainence plan for CI - james_w will ensure this is part of the
current project.
Thanks,
James
Follow ups
References